API RP 580

Elements of a Risk-Based Inspection Program

องค์ประกอบของโปรแกรมตรวจสอบตามความเสี่ยง

Organization
API
Category
NDE / Inspection
Edition
2023
Region
US / International
Last Reviewed
2026-07-01
Status
reviewed
1

Overview

Minimum program elements for developing, implementing, and maintaining risk-based inspection.

2

Scope & Applicability

Applies To Industries

RefineryPetrochemicalChemical Plant

Covers — the required elements of a risk-based inspection (RBI) program: data collection, damage-mechanism identification, probability-of-failure and consequence-of-failure assessment, risk ranking, inspection planning/effectiveness, reassessment, management of change, and roles/qualifications.

Does NOT cover (exclusions) — the following are governed elsewhere:

  • The quantitative POF/COF calculation methodology → API RP 581.
  • Damage-mechanism descriptions → API RP 571.
  • The baseline inspection code (interval caps, rerating) → API 570 / 510.

RP 580 defines what an RBI program must contain; RP 581 provides one quantitative way to calculate the risk.

3

Key Requirements

RP 580 sets the program elements for RBI:

  • Data & Damage Mechanisms — collect equipment data and identify credible damage mechanisms (per RP 571).
  • Risk Assessment — evaluate probability and consequence of failure and rank risk.
  • Inspection Planning — set inspection scope, method, and interval by risk and inspection effectiveness.
  • Reassessment & Roles — update on change/new data, with defined roles and qualified personnel.
4

Technical Details

API RP 580 defines the elements a risk-based inspection (RBI) program must contain: data, damage-mechanism identification, probability and consequence of failure, risk ranking, risk-driven inspection planning, reassessment, and qualified roles. It directs inspection resources by risk — more effort on high-risk equipment, less on low-risk — rather than by fixed intervals alone.

It is deliberately methodology-neutral: RP 580 says what a credible program must include, while the quantitative POF/COF calculation is provided by API RP 581. RBI plans made under 580/581 can replace the default fixed intervals of API 570/510.

Engineering Note: An RBI program is only credible if its damage-mechanism identification (RP 571) is complete — missing a credible mechanism produces a falsely low risk ranking and an inspection plan that never looks for the threat that actually fails the equipment.

5

Engineering Notes

The "what a good RBI program must contain" standard — it defines the elements (data, damage-mechanism identification, probability and consequence of failure, risk ranking, inspection planning, reassessment, roles/qualifications) without prescribing a specific calculation. It lets inspection effort be directed by risk: high-risk equipment gets more/better inspection, low-risk gets less. The quantitative methodology that implements it is API RP 581.

7

Source, Edition & Status

Publisher
API
Edition Year
2023
Industries
Refinery, Petrochemical, Chemical Plant
Last Reviewed
2026-07-01
Last Updated
2026-07-01
Verified By
Engineering content reviewer
Content Status
reviewed
Official Link
www.api.org
Disclaimer: Disclaimer: This page provides a simplified engineering reference only. It is not a replacement for the official standard. For design, inspection, procurement, and construction, always refer to the latest official standard and the applicable project specification.